An Interesting Question on Garment SAM Calculation and Use of Rating Factor
An OCS reader wrote me following mail. Go through it and try to find out how would you explain him to solve his problem.
"I have a question about calculating SAM for an operation or a garment.
If you use the formula
Basic time= Observed time * performance rating and use a
higher performance rating the time taken for the operation is higher
than if you took a lower performance rating that is lower.
For example. observed time is 10 minutes. with this - if the operator is at 100% performance then the operation's Basic time (SAM value) will be 10 minutes (10X1). But if an operator is at 50% performance (meaning half as efficient as an operator at 100% performance) for with the same average time for an operation then basic time is 5 (10 x 0.5) Is this to mean that a lower operator performance will yield faster completion of garment making tasks? that seems counter intuitive to me. Please explain"
I answered him with following explanation.
For example. observed time is 10 minutes. with this - if the operator is at 100% performance then the operation's Basic time (SAM value) will be 10 minutes (10X1). But if an operator is at 50% performance (meaning half as efficient as an operator at 100% performance) for with the same average time for an operation then basic time is 5 (10 x 0.5) Is this to mean that a lower operator performance will yield faster completion of garment making tasks? that seems counter intuitive to me. Please explain"
For a while I also started thinking, how it is coming? A higher rated
operator taking higher time than the low rated operator. I know it is
not true. But where the problem lies in above example?
You are going set standard time (SAM) of an operation through time
study. First you need to calculate Basic Time. You need to level the
observed time (cycle time) to get standard time. And leveling of time is
done by multiplying Rating factor (performance rating).
Formula: Basic time = Observed time X Rating
(If we do not consider allowances, Basic time=standard time)
Example, You timed one operator and it is 10 minutes, you rate her 50%. As the operator's rating is less than 100%, she would take higher time than the standard time. And standard time would be lower than 10 minutes. Right?
Example, You timed one operator and it is 10 minutes, you rate her 50%. As the operator's rating is less than 100%, she would take higher time than the standard time. And standard time would be lower than 10 minutes. Right?
So you multiply rating with observed time to calculate basic time. And
it is (10 * 50%) = 5 minutes. It means an operator who works at normal
pace (no too fast or no too slow) should take 5 minute to complete this
operation. For same operator, taking 10 minutes to compete that
operation and you rate her 100%. Logically, it is not possible. Either
you timed wrong or rate her incorrectly.
In reverse way, a 100% operator and a half efficient (50%) operator can not complete a task in same time (10 minutes). Your assumption is wrong in the above example.
Conclusion: A low performance operator would take higher time to complete the given operation than a higher performance operator.
In reverse way, a 100% operator and a half efficient (50%) operator can not complete a task in same time (10 minutes). Your assumption is wrong in the above example.
Conclusion: A low performance operator would take higher time to complete the given operation than a higher performance operator.