How to Calculate Lead Time for Stitching Process?
The question I am going to ask is the basic of the manufacturing industry.
Q-1: How can I calculate Lead Time for stitching process?
Q-2: Should we always consider style category proportion (Basic, semi fashion, Fashion & H fashion) while calculating Lead time for a stitching facility? Waiting for your prompt response. ... asked by Sohaib Abbas
Answer
While I was reading this question, suddenly one of my real life story came in my mind. A similar question I have faced 7 years ago. I appeared in a job interview for production planning job. Interviewer gave me a problem and I had to solve that. Problem was as following
"Suppose you receive an order of 5000 pieces. you have two sewing
lines to run the style and average production per day per line is 400
pieces. Calculate how many days it would take to complete stitching?"
I was in hurry to answer the question. I thought it is a very simple
question. It can be solved easily by mathematical calculation. On a
paper I did a simple calculation and replied it would be 7 days.
My calculation was
Production per day from two lines = 400 X 2 = 800 pieces
Total production requirement is 5000 pieces
So, production time in days would be = (5000/800) = 6.25 days and rounded off 7 days.
My answer was wrong. The interviewer explained me that I couldn't make it in 7 days.
First reason, from day one I would not get the production of 400 pieces
from each line. So need to consider production build up time.
Second reason, I need to add extra cutting quantity to the order to find
total quantity to be stitched. And considering these I had to calculate
production time for that order.
That was the story. Unfortunately, I did not get that job.
Let me explain answers of today's questions.
Answer of Question #1.
The same principle you need to apply when you calculate Lead Time of the
Stitching Process for your orders. Here is the lead time calculation
procedure -
Step#1. Find Production build up time. I mean how much time a line takes to reach pick production. This is also known as learning curve. If know learning curve, you can calculate day wise production up to pick production.
Step#1. Find Production build up time. I mean how much time a line takes to reach pick production. This is also known as learning curve. If know learning curve, you can calculate day wise production up to pick production.
Step#2. Calculate average production capacity of your line daily from the garment SAM and avergae line efficiency.
Step#3. As said above, if you cut extra quantity add that to your total production quantity
Step#4. Finally calculate the lead time adding days required to complete stitching the full order.
Example:
Example:
Suppose you got an order of 4000 pieces. No extra cutting. On 4th day
after loading a style you reach to pick production. Based on learning
curve production on
Day 1- 100 pieces
Day 2- 250 pieces
Day 3- 450 pieces
Day 4 and onward 500 pieces.
So in the initial 3 days line you will get production of 800 pieces and later 500 piece/day
So stitching lead time
So stitching lead time
= (3 days+(4000-800)/500) days
= 3+6.4 days = 10 days
Day wise production in initial days (production build up days) to be calculated from learning curve.
Day wise production in initial days (production build up days) to be calculated from learning curve.
Answer of Question #2.
Production build up time varies product to product. So yes, you have to consider product categories while calculating lead time.
No comments:
Post a Comment